Maximized production area
Better working condition & easily transporting goods
Good ventilation
Security assurance
Capacity ~20 - 50 bikes
Easy access for containers
Capacity 400 persons
CCTV & lighting in common area
approx. 60 km
approx. 60 mins
Ha Noi - Thai Nguyen Highway
approx. 30 km
approx. 30 mins
Ha Noi - Thai Nguyen Highway
approx. 120 km
approx. 120 mins
18 Highway
approx. 150 km
approx. 150 mins
5A Highway or Ha Noi - Hai Phong Highway
approx. 140 km
approx. 140 mins
1B Highway
Size | ~2,000 – 3,000 – 5,000 m2 (Combined units available upon request) |
---|---|
Electrical Provision | 250 ~ 500 KVA / 3-phase power |
Roof | Stainless metal sheet with insulation layers and skylight |
Canopy | 4 m (W) x 129 m (L) |
Wall | 1.2 m brick wall & ~ 8.8 m stainless metal cladding on top |
Ventilation | Ventilation louvers at both side of factory |
Floor Loading | 2 tons/m2 |
Internal Partition | Fixed partition, fire retardant coating |
Roller Shutter | 4 m (W) x 5.2 m (H) |
Fire Protection System | Fire sprinkler system |
Technical Highlights | ● Wide internal road, easy for loading ● Parking lot & canteen ● CCTV & lighting in common area ● 24/7 security |
Sustainable Environment | Clean, light industries |
Lease Term | 3 – 5 – 10 years |
Category | Description | Remark |
---|---|---|
Power System | • Electricity supplied from 3 capacity 2x63MA – 110/22kV transformer substations for Industrial Park
• Power supplied from 2 separate sources to avoid • Standard main distribution board for connecting |
Tenant signs contract directly with Vietnam Electricity (EVN)
(*) Off-peak hours: 1,007 VND/kWh |
Water System | • Water supplied from Yen Binh Water Plant
• Capacity 150.000 m3/ day-night |
Tenant signs contract directly with Yen Binh Fresh Water JSC (YBW)
Price: 12,500 VND/m3 |
Waste Water Treatment | The cost depends on each package and supplier | Wastewater is equal to 80% of the clean water use Price: 12,000 VND/m3 |
Telephone/ Internet System |
Available telecommunication infrastructure of Viettel and VNPT | Tenant signs contract directly with their own supplier |
Garbage | Pricing subjects to 3rd party supplier | Tenant signs contract directly with their own supplier |
* Off-peak hours |
---|
Applying for all days from 22:00 – 04:00 next day |
** Normal hours | |
---|---|
Monday to Saturday | From 04:00 – 09:30 From 11:30 – 17:00 From 20:00 – 22:00 |
Sunday | From 04:00 – 22:00 |
*** Peak hours | |
---|---|
Monday to Saturday | From 09:30 – 11:30 From 17:00 – 20:00 |
Sunday | No peak hours |
FY 2019 | Labor Supply (persons) | Immigration rate (%) |
---|---|---|
Thai Nguyen | 800,000 | 50% |
Zone | Minimum wage per month |
---|---|
Zone 2 | 3,920,000 VND (~170 USD) |